Checking the walls before starting any work is the first step we perform during the first contact with our clients.
STAGE 2
Removing the plaster during the first stage of the commencement of works and making a new one (DPC-Injection) from the inside and outside due to the wall thickness and condition.
STAGE 3
Damp Proofing Drying process after insertion of Dehumidifier, visible traces of salt coming out of New (DPC Injections) This process shows us how strong the salinity is in the walls; the salt in the walls keeps the water in the walls. Our (DPC-Injections) extract salt from the walls to reduce the persistence of water or dampness in the walls.
STAGE 4
Due to the thickness of the scan, the Dehumidifier drying process was extended by one week and was completed. After thorough drying of the walls, a waterproof plaster was applied, including Tanking Slurry, to protect the walls against moisture.
STAGE 5
Date of the completion of work 15/12/21
20/05/22 – Checking the walls after finishing our works
Result of visit There are no signs of flaking paint, no bubbles and no smell of dampness.